Migrate all appropriate resources in the server room to Azure cloud hostin
Supports the move of TBR to new headquarters
Move to new headquarters tentatively scheduled for September 23
Oracle software has been installed on several servers
Some initial Banner services have been moved to new systems for initial configuration and setup (i.e., the jobsub server for compilers and communication testing)
Banner databases are to be restored onto the new system
Backups of the existing Middle Tier servers are being configured for INB/SSB operations, Extended Banner services (i.e., BEIS) is scheduled for setup and installation is scheduled for early to mid July
The process is about 75% finished with less than 5 servers remaining to move.
All DNS services have been migrated to Azure.
Final piece involves O365 and moving the local shared drive and documents into SharePoint and OneDrive for Business